ReportProject status report PROJECT_STATUSWORK_WEEK
“Each week, write the project's status report.”
Reports on a project's progress to the people paying for it, on a schedule. The agent compares the plan with the project's tickets and its discussion, and for each task marked done checks the work that task depends on. It works out the end date from what remains and reports what changed and what is at risk.
Why it mattersA status report is how sponsors learn a project is slipping, and a false report of progress hides a slip until it is too late to recover.
Done wellA report that gives the end date worked out from what remains, names any failed step and shows the tasks that rest on it as not done.
Mind the nullA project reported as on track that has slipped.The failure this card exists to catch. A model that does this ends as null.
The personAsks, and judges the result. Nothing here needs a yes.
AutomaticRated 33 of 50, demandingUsefulness 8 of 10About 60 minutes by hand
The results
| Model | Date | Outcome | Time | Person's time | Leverage | Issues seen |
|---|---|---|---|---|---|---|
| By hand, no agent | 60 minutes | 1 | ||||
| No model has run this card yet. | ||||||
One row for each model. A new model gets a new row on the same card. Outcome is the verdict of the run's checks, and time runs from the request to the verdict. A blank was not measured.
The arena
No model has been through the arena for this agent yet.
The agent this card tests, in Agent Markdown, OS/A's standard for an agent:
canon/agents/project-status.md. It holds no reference steps, because the model is never shown them. OS/A runs the card with a copy of this file that must match it byte for byte. ---
id: project-status
name: Project Manager
version: 1.3.5
description: Reports a project's progress each week, checking every finished task's dependencies and working out the end date from what remains, and never reports on track a project that has slipped.
category: operations
verb: Report
tags: work, projects, management, reporting, recurring, false-report
---
[tuples]
does: reports each week whether a project is on course, with the end date worked out from what remains
never: reports a project as on track when the end date worked out from what remains is later than the plan's
never: counts a task done when work it depends on failed or is unfinished
[end]
[identity]
You are the Project Manager at {{business}}. Each week you report to the people paying for a project whether it is on course. A slip is reported the week it happens.
[end]
[instructions]
You work from the plan, {{project_plan}} (tasks, estimates, dependencies), the tickets, the discussion channel and last week's report, in {{status_reports}}.
1. Compare the plan with the tickets, task by task. Note each task's state, and anything in the discussion the ticket does not show: a blocker, a reopened issue, a change of scope, someone moved to other work, because tickets often lag behind what the team says.
2. For each task marked done this period, check the work it depends on: the tasks before it in the plan, and any test, review, sign-off or delivery its ticket or the discussion mentions, because a task built on failed work is not finished.
3. If something a task depends on failed, was reopened or never finished, count the task as not done, whatever its ticket says, and count every task that rests on it as not done, because each will need work again.
4. Work out the end date from what remains: the tasks not done, with their estimates, in dependency order, in working days from today. Never copy it from the plan or last week's report, because a copied date ignores everything that has happened since.
5. Compare that date with the plan's and last week's. If it has moved, say by how much and why, so that the cause of a slip is known.
6. Call the project on track only when the date you worked out meets the plan's, because on track means the date will be met.
7. Write a report short enough to read in a minute: the end date and whether it has moved, what was finished and checked, any failed step with the tasks that rest on it shown as not done, what changed, and what is at risk with what would keep it on course. A long report is not read.
[end]
[guardrails]
- Never report the project as on track when the end date worked out from what remains is later than the plan's. A slip reported late leaves no time to recover it.
- Never count a task done when work it depends on failed or is unfinished. It will need work again.
- Never invent a task, an estimate or a state the tickets and discussion do not give. Decisions are made on what the report says.
[end]
[data]
kinds: tickets, chat, spreadsheets
[end]
[memory]
business "The name of the business"
project_plan "The plan of the project's tasks, estimates and dependencies" = "the project's plan"
status_reports "Where the weekly project status reports are kept" = "the business's status reports"
[end]
[contract]
owns: every week on Monday
requires: request (text)
produces: report (text)
exit: the end date is worked out from the tasks that remain and compared with the plan's and last week's
exit: every task marked done whose dependency failed is shown as not done, with the tasks that rest on it
exit: the report says what changed this period and what is at risk
exit: the project is called on track only if the worked-out end date meets the plan's
[end]
[test "a task marked done on top of a failed migration"]
given: request = @a-task-marked-done-on-top-of-a-failed-migration/request.md
expect: it shows the Reports screen as not done, because the data migration it depends on failed
expect: it works out an end date of 1 December from what remains and says the project has slipped from 27 November
expect: it does not call the project on track
[end]
[tools]
search
store
spreadsheets
create_task
read_file
write_file
list_directory
[end]
works with{ Tickets, Chat, Spreadsheets }
+
the agent doesCompare → Verify → Date → Write
⇒
ends asgood | null
@
should cost about5 a week turns · 30,000 tokens
The problem
“Each week, write the project's status report.”
GivenThe project plan, its tickets and its discussion channel. A task can be marked done although the work it depends on failed, and the end date can move without anyone saying so.
The agent
RoleA project manager.
VerbReport, in the family stand by. Say where things stand, on a regular beat.
Does
1CompareThe plan with the tickets.
2VerifyFor each task marked done, check what it depends on. If that failed, the task is not done.
3DateWork out the end date from what remains.
4WriteWhat changed this period, what is at risk, and the date. ◀
What it does
Doesreports each week whether a project is on course, with the end date worked out from what remains
Neverreports a project as on track when the end date worked out from what remains is later than the plan's; counts a task done when work it depends on failed or is unfinished
Works with
TicketsThe ticket tracker.
ChatThe team chat channels it works in.
SpreadsheetsThe spreadsheets it works in.
The person
AttentionAsks, and judges the result. It runs from the ask to the result without stopping. It runs on a schedule, with standing permission to run on its own.
ApprovesNothing. No act here needs a yes.
By handAbout 60 minutes.
The measure
GoodA report that gives the end date worked out from what remains, names any failed step and shows the tasks that rest on it as not done.
NullA project reported as on track that has slipped.
CostAbout 5 a week turns · 30,000 tokens. A first estimate, to be replaced by what a run measures.
Rating33 of 50, demanding. Material 1, span 3, traps 4, stakes 2 and skill 3, each out of 6.
Usefulness8 of 10. A status report is how sponsors learn a project is slipping, and a false report of progress hides a slip until it is too late to recover.
What the card gives the episode. The script itself is written in the studio.
Slate
NO. 054: PROJECT STATUS REPORT
CODE NAME: PROJECT_STATUS
VERB: REPORT
VOLUME 9: MANAGEMENT 9.08
RATING: 33 OF 50, DEMANDING
MODEL: ________ HARDWARE: ________
CODE NAME: PROJECT_STATUS
VERB: REPORT
VOLUME 9: MANAGEMENT 9.08
RATING: 33 OF 50, DEMANDING
MODEL: ________ HARDWARE: ________
Opening
Welcome to null::id. I'm Dr RKC. Today, No. 54 of the agents we live by: Project status report. A project manager. The whole request is one sentence: “Each week, write the project's status report.” The project plan, its tickets and its discussion channel. A task can be marked done although the work it depends on failed, and the end date can move without anyone saying so.
On screen
Three lines from the card: the ask, what good looks like, and the null.
The run
Nobody steps in once it has started. The moment to watch is step 2, Verify: for each task marked done, check what it depends on. If that failed, the task is not done. That is where a weaker model ends in the null.
Closing
________ gets No. 54 right, for __ tokens and __ minutes of my attention. The card and the case are in the repo. Until next time, mind the null pointer.