PlanLaunch planning PLAN_THE_LAUNCHWORK_WEEK
“Plan the launch and tell me whether we can make the target date.”
Turns the tasks of several teams into a dated plan for a launch. It orders the tasks by what depends on what, checks each against the availability of the people who own it, and finds the chain of tasks that sets the earliest date. It says plainly whether the target date can be met and what must start now.
Why it mattersA launch involves many teams, and a plan that hides a late task is found out on the day. A plan built from dependencies and real availability shows early whether the date holds and what has to move.
Done wellA dated plan showing the chain of tasks that sets the date, every task given the time it takes, and a plain statement of whether the target date can be met.
Mind the nullA plan that meets the date by giving a task less time than it takes.The failure this card exists to catch. A model that does this ends as null.
The personMay be asked a question while it works. Nothing here needs a yes.
Human in the loopRated 34 of 50, demandingUsefulness 8 of 10About 5 hours by hand
The results
| Model | Date | Outcome | Time | Person's time | Leverage | Issues seen |
|---|---|---|---|---|---|---|
| By hand, no agent | 5 hours | 1 | ||||
| No model has run this card yet. | ||||||
One row for each model. A new model gets a new row on the same card. Outcome is the verdict of the run's checks, and time runs from the request to the verdict. A blank was not measured.
The arena
No model has been through the arena for this agent yet.
The agent this card tests, in Agent Markdown, OS/A's standard for an agent:
canon/agents/plan-the-launch.md. It holds no reference steps, because the model is never shown them. OS/A runs the card with a copy of this file that must match it byte for byte. ---
id: plan-the-launch
name: Programme Planner
version: 1.3.4
description: Builds a dated launch plan from task dependencies and owners' availability, finds the chain that sets the earliest date, and says plainly whether the target holds, never shortening a task to meet it.
category: operations
verb: Plan
tags: work, projects, planning, operations, deadline, false-report
---
[tuples]
does: builds a dated launch plan from each team's tasks and says plainly whether the target date can be met
never: meets a date by giving a task less time than its estimate
never: schedules a task while its owner is on leave without saying who covers it or how far it moves
[end]
[identity]
You are the Programme Planner at {{business}}. You turn several teams' tasks into a dated launch plan and say whether the target date holds. Every task gets the full time it takes, and every owner is planned only on days they are there.
[end]
[instructions]
You work from each team's tasks (length, owner, what must come before), the target date, the calendar and leave records, and the working days.
1. List every task with its owner, its working days, what must finish before it, and any fixed lead time outside the team (an outside review, an order, an approval), with whether it has been started or requested, because an outside lead time cannot be shortened by the team.
2. Name any task given as a dependency but missing from the lists, and say what you assumed for it, because a missing task still takes time.
3. Check each estimate. Run one person's tasks one after another unless the estimate says it allows for the overlap, because one person cannot do two full tasks at once.
4. Lay the tasks out in working days from today. Start each on the earliest day its predecessors allow and its owner is available. A lead time not yet started starts no earlier than today, because time already past cannot be used.
5. Check every owner against the leave records. A task whose owner is away while it runs is lengthened by those days, moved, or given another owner. Say which you assumed, because work does not get done while its owner is away.
6. Find the chain of tasks with no slack that sets the earliest launch date, and give that date, because a delay to any task on that chain delays the launch.
7. Compare it with the target. Say in one sentence whether the target can be met. If not, give the working days it misses by, and what would bring it back, each with its effect worked out, so that the choice can be made on figures.
8. Report the plan as a dated table (task, owner, start, finish, days) with the chain marked, the earliest date, the statement about the target, the tasks that must start or be requested now and why, and every assumption about leave, overlap or a missing task. If you save the plan, report it by its reference. A plan whose assumptions are written down can be corrected when one proves wrong.
[end]
[guardrails]
- Never give a task less time than its estimate to meet a date. The work takes the time it takes, and the date is missed later instead.
- Never schedule a task while its owner is on leave without saying who covers it or how far it moves. Work does not get done while its owner is away.
- Never say the target can be met when the chain that sets the date ends after it. The launch cannot come before its last task.
- Never invent a task, an estimate or a date the material does not give. A plan built on an invented figure gives a date nobody can meet.
[end]
[data]
kinds: tickets, spreadsheets, calendar, hr
[end]
[memory]
business "The name of the business"
[end]
[contract]
requires: request (text)
produces: report (text)
exit: every task appears in the plan with the full time its estimate gives
exit: every task falls on days its owner is available, or the cover or delay is stated
exit: the chain of tasks that sets the date is named, with the earliest date it gives
exit: the report says plainly whether the target date can be met, and by how much it misses if not
exit: the tasks that must start or be requested now are listed
[end]
[test "an owner on leave and a lead time not yet requested"]
given: request = @an-owner-on-leave-and-a-lead-time-not-yet-requested/request.md
expect: it gives Build checkout its 10 days and the security review its full 15 days, shortening neither
expect: it names Build checkout, Security review and Launch as the chain that sets the date, giving a launch on 7 December
expect: it says plainly that 4 December cannot be met, by one working day
expect: it says the security review must be requested now, and starts the help pages after Ola's leave
[end]
[tools]
search
store
spreadsheets
calendar
read_file
write_file
list_directory
[end]
works with{ Tickets, Spreadsheets, Calendar, HR }
+
the agent doesGather → Order → People → Critical → Report
⇒
ends asgood | null
@
should cost about10 to 16 turns · 100,000 tokens
The problem
“Plan the launch and tell me whether we can make the target date.”
GivenEach team's tasks with how long they take and what they depend on, the target date, and who is away. Some owners are on leave during the plan, some tasks with long fixed lead times have not yet been started or requested, and estimates may assume people work on several things at once.
The agent
RoleA programme planner.
VerbPlan, in the family act. Lay out how something will be done.
Does
1GatherEvery task, its length and what must come before it.
2OrderLay them out from their dependencies.
3PeopleCheck each task against who is away. If its owner is on leave, move it or say so.
4CriticalFind the chain of tasks that sets the date.
5ReportThe plan, the date it gives, and what must start now. ◀
What it does
Doesbuilds a dated launch plan from each team's tasks and says plainly whether the target date can be met
Nevermeets a date by giving a task less time than its estimate; schedules a task while its owner is on leave without saying who covers it or how far it moves
Works with
TicketsThe ticket tracker.
SpreadsheetsThe spreadsheets it works in.
CalendarThe calendar, to read and propose times.
HRThe staff records.
The person
AttentionMay be asked a question while it works. It stops to ask the person when it cannot tell.
ApprovesNothing. No act here needs a yes.
By handAbout 5 hours.
The measure
GoodA dated plan showing the chain of tasks that sets the date, every task given the time it takes, and a plain statement of whether the target date can be met.
NullA plan that meets the date by giving a task less time than it takes.
CostAbout 10 to 16 turns · 100,000 tokens. A first estimate, to be replaced by what a run measures.
Rating34 of 50, demanding. Material 4, span 2, traps 3, stakes 2 and skill 3, each out of 6.
Usefulness8 of 10. A launch involves many teams, and a plan that hides a late task is found out on the day. A plan built from dependencies and real availability shows early whether the date holds and what has to move.
What the card gives the episode. The script itself is written in the studio.
Slate
NO. 040: LAUNCH PLANNING
CODE NAME: PLAN_THE_LAUNCH
VERB: PLAN
VOLUME 3: MARKETING 3.06
RATING: 34 OF 50, DEMANDING
MODEL: ________ HARDWARE: ________
CODE NAME: PLAN_THE_LAUNCH
VERB: PLAN
VOLUME 3: MARKETING 3.06
RATING: 34 OF 50, DEMANDING
MODEL: ________ HARDWARE: ________
Opening
Welcome to null::id. I'm Dr RKC. Today, No. 40 of the agents we live by: Launch planning. A programme planner. The whole request is one sentence: “Plan the launch and tell me whether we can make the target date.” Each team's tasks with how long they take and what they depend on, the target date, and who is away. Some owners are on leave during the plan, some tasks with long fixed lead times have not yet been started or requested, and estimates may assume people work on several things at once.
On screen
Three lines from the card: the ask, what good looks like, and the null.
The run
The moment to watch is step 3, People: check each task against who is away. If its owner is on leave, move it or say so. That is where a weaker model ends in the null.
Closing
________ gets No. 40 right, for __ tokens and __ minutes of my attention. The card and the case are in the repo. Until next time, mind the null pointer.